We use functional cookies for a number of reasons, such as keeping the Costain website reliable and secure and to analyse how our site is being used.
Will you accept our use of non-essential cookies?



Yes No Privacy Notice

Keeping Londoners connected to a safe and reliable electricity supply

The London Power Tunnels project has created a new 32km electricity superhighway deep below the capital, which helps keep Londoners connected to safe and reliable electricity supplies.

  • Service 1

National Grid

  • Service 1

Skanska

  • Service 1

Complex programme delivery

Key benefits

71,428

miles reduced from vehicle mileage footprint which equates to 149tCo2eq

4,838

wagon movements removed from UK roads, resulting in an estimated carbon saving per site from 5,6tCo2eq to 217.50tCo2eq

89.7% score

Whole Project CEEQUAL (Civil Engineering Environmental Quality) Assessment awarded Excellent by BRE.

10kg

of CO2 emissions saved per day (on average) through the use of electric cars when travelling between sites

The most significant addition

to the capital’s electricity system since the 1960s.

London currently accounts for 20 percent of the UK’s electricity usage - a demand that is increasing year by year. In order to supply the city’s substations with the necessary energy to keep up with demand, Costain working in joint venture with Skanska [CSJV] on behalf of National Grid, has constructed approximately 32km of a high voltage electricity cable tunnel. This runs between Hackney and Willesden (via Kensal Green) and Wimbledon. Work also included the construction of 14 access shafts and associated head houses and culverts. 

Instead of digging up and replacing the old cables that are buried under the roads – adding years of roadworks to London’s already busy transport network – CSJV created an easily accessed space that allowed cable installation and maintenance to be carried out without any disruption to the public. It allowed extra room for additional cables that could be laid to meet future demand.

A sustainable solution

Construction of the tunnels and associated infrastructure produced approximately 400,000m3 of excavated material.  There was very little opportunity to re-use this material within the project, so it needed to be removed from worksites.  At the time, our client was carrying out decommissioning and remediation works at gas holder sites within London and required a suitable fill material. 

Early planning with stakeholders led to the successful coordination and collaboration between the various project teams who quickly recognised the potential financial and sustainability benefits including the carbon reduction generated by diverting excavated London clay from the project to our client’s gasholder and remediation sites.  Approximately 48,386m3 of the spoil diverted from landfill was moved by using the CL:AIRE Definition of Waste Code of Practice to transfer material under direct transfer.

This enabled to significantly reduce hauling distances by 21% to 88% to the alternative landfill disposal option, as the proposed sites were within 2 to 14 miles of the London Power Tunnel sites. This also enabled to remove 4,838 wagon movements off UK roads, resulting in an estimated carbon saving per site from 5,6tCo2eq to 217.50tCo2eq.  Avoiding disposal and movements to and from sites enabled the London Power Tunnel project to reduce its vehicle mileage footprint by an estimated 71,428 miles which equates to 149tCo2eq and provided a substantial cost savings of £2,936,933.00 to the project.
 

"The London Power Tunnels project is seen as major success story within National Grid. Costain has been the key contract partner for the London Power Tunnels (LPT) project since 2010 constructing vital assets in challenging environments. The vast scale of the undertaking is sometimes easy to forget; with 32km of tunneling crossing 37 existing tunnels. Work completed without incident and with real innovation in managing and monitoring settlement yielding strong performance, At the peak of the programme Costain were working across 12 London sites – each with their own unique challenges. There is a palpable sense of pride within the National Grid and Costain teams (current and former) at what has been achieved. How it has been achieved with collaboration and innovation should also be celebrated."

Gareth Burden, National Grid Senior Project Manager
Nissan Leaf electric vehicles

Related news

Contact and social

Energy

Laura Hughes, Sector Director - Energy
01628 842444
[email protected]