We use functional cookies for a number of reasons, such as keeping the Costain website reliable and secure and to analyse how our site is being used.
Will you accept our use of non-essential cookies?



Yes No Privacy Notice

Complex Concrete Poured To Perfection

Costain Skanska

6 October 2015

The team on the Costain Skanska joint venture (CSJV) Crossrail C360 Eleanor Street and Mile End Park contract has concluded a highly challenging series of more than 90 secondary lining concrete pours.

The work, which involved lining the shafts and adits – short tunnels leading from the base of the shafts to the main Crossrail running tunnels under East London – took six months until the final pour was completed.

The primary lining of the 36-metre-deep shafts consisted of cast concrete rings against the exposed ground. The lower section of the shaft at adit level, and the adit primary lining was formed using shotcrete. The secondary linings were composed of poured concrete.

Normally, there would be a single adit between the base of a shaft and a running tunnel. This was not possible for technical reasons for the ventilation design requirements, so the adit had to split in two – and then split again – to give four passages to each running tunnel, giving eight connections in total.

“This gave us some very complex geometry,” said CSJV Project Manager, Stephen Duncan. “Normally, you have the same profile and can use the same shuttering and just move them 20 metres or so every few days. With this project, we had a lot of different profiles and sometimes only got to use the same shutters two or three times.”

A further complication came from the fact that the shafts were completed before the running tunnels passed by. Without the space normally afforded by the running tunnels in which to work, the secondary lining process had to proceed in unusually tight confines. “Traditionally, we build parts of these linings from the running tunnels as we work on two fronts to complete the secondary linings,” said Stephen. “The team here came up with a better temporary works solution to allow us to do the shafts and adits at the same time.”

According to Steve Harvey, Managing Director at Joseph Gallagher: “The project was one of the most technically challenging sprayed concrete and insitu lining projects our business has ever undertaken.

“The job comprised elliptical adits of various sizes from 3.5 metres up to seven metres across. These resulted in multiple complex junctions between adits and the running tunnels, requiring purpose-made bespoke shuttering.

“The success of the project was built around a collaborative approach between client, CSJV and Joseph Gallagher Ltd, which put the safety of the workforce above all else.”

Overall, the C360 contract has gone 670 days, the entire duration of shaft and adit contruction, without a single reportable accident.

 


Caption: A shift team pauses for a photo as the final concrete pour is completed.

 

 

Ends

 

 

Media Enquiries 
Costain Communications Department 
01628 842585
[email protected]